Friday, November 27, 2009

November Update

November 2009 was the fourth wettest November in 75 years. This had ill effects on the construction site. Concrete placements, site work (earth-moving), and masonry work were all negatively effected. Though time was lost due to weather, we were still able to get started on the brick work on the outside of the theater building. The second floor in the elementary school wing and the north end of the first floor of the Middle School wing were placed. Structural steel was erected in Middle School along with the support system for the second floor.

No comments: