September Update

September brought very good working conditions: long sunny days and warm temperatures. English and their workforce were able to achieve three main accomplishments. First, we completed the Field Turf girls' lacrosse field. Next, the geothermal vault was buried. This is a distribution hub where all of piping that runs through the 140 geothermal wells is consolidated into one pipe leading into the building. Finally, AG Dilliard installed a temporary parking lot across the street from the lacrosse field to accommodate parking for construction vehicles and football and lacrosse parking.